Maentwrog Hydro Power Station Optimisation Services
Nuclear Decommissioning Authority
This tender has closed
The submission deadline for this contract has passed. There may be more active services tenders from Nuclear Decommissioning Authority, and hundreds more across the UK public sector.
Key details
Procurement
- 71314000 Energy and related services
- 38551000 Energy meters
- 65300000 Electricity distribution and related services
- 09310000 Electricity
- 72227000 Software integration consultancy services
- 71241000 Feasibility study, advisory service, analysis
- 79930000 Specialty design services
- 71314300 Energy-efficiency consultancy services
- 31682000 Electricity supplies
- 72228000 Hardware integration consultancy services
- 09300000 Electricity, heating, solar and nuclear energy
- 65400000 Other sources of energy supplies and distribution
- 71314200 Energy-management services
- 65410000 Operation of a power plant
- 51112200 Installation services of electrical equipment
What happened
Nuclear Decommissioning Authority awarded this contract to Gridbeyond Ltd worth £1,092,000 on 31 Jul 2026. The contract runs until 4 Oct 2028.
Description
NDA is a non-departmental public body charged, on behalf of government, with the mission to clean-up the UK’s earliest nuclear sites safely, securely and cost effectively. We’re committed to overcoming the challenges of nuclear clean-up and decommissioning, leaving the 17 nuclear sites ready for their next use. We do this work with care for our people, communities and the environment, with safety, as always, our number one priority. We also play an important role in supporting government’s aspiration for the UK to be a global leader in the civil nuclear sector. We strive to deliver best value for the UK taxpayer by focusing on reducing the highest hazards and risks, while ensuring safe, secure, and environmentally responsible operations at our sites. We seek ways to reduce the level of public funding from government by generating revenue through our commercial activities.
Maentwrog Hydroelectric Power Station (“Maentwrog”) is a 28MW hydroelectric plant owned by NDA and operated by Magnox Limited (“Magnox”).
The NDA is seeking to engage with economic operators obtain feedback regarding a forthcoming tender to appoint an economic operator to deliver energy generation and trading optimisation services for the NDA's Maentwrog Hydropower station asset. The core service to be delivered includes, but is not limited to the provision of trading available energy generation capacity within the wholesale market, based upon fundamental and technical analysis, market expertise and available generation capacity based upon water volumes, rainfall and available measurements within defined operational parameters.
The aim of this procurement is to increase income generation to support the NDA in delivering it's mission.
It is anticipated that the agreement may be based upon a 2 year initial term with 2 twelve month optional extensions.
It is anticipated that the total contract value will be circa £240,000 and £500,000 for the initial term, with a potential income value between £480,000 and £800,000 across a potential total 4-year term, subject to Supplier performance. Please note, we appreciate that income will change based upon market conditions and fluctuations, therefore these are indicative estimates.
Awarded supplier
Contact
Identifiers
Explore related tenders
Other tenders from Nuclear Decommissioning Authority
View all →External ID: fts-ocds-h6vhtk-056518 • Added 21 July 2026