Manchester International Airport - Precast Concrete Beams
Kier Transportation - CP7 NWC
This works tender from Kier Transportation - CP7 NWC closed on 20 Jul 2026. Estimated value £500,000. The contract end date is 17 Mar 2027. Region: North West.
Live now: tenders like this
- Manchester International Airport Phase 2 - Platform CivilsKier Transportation - CP7 NWC£2,500,000 · Closes 4 December 2026
- London and Quadrant Housing Trust - Supply/Distribution of Concrete Blocks Dynamic Purchasing System (DPSL&Q Supply Chain Management (London and Quadrant Housing Trust)Closes 10 March 2031
- Qualification system for the services of production and delivery of pre-cast and pre-stressed reinforced concrete structuresIarnród Eireann-Irish RailCloses 14 March 2027
- NNLC484D - Operations, Site Work and Facilities Management Dynamic Purchasing SystemUnited Kingdom National Nuclear Laboratory£15,000,000 · Closes 8 January 2029
- Provision of Surface Dressing ChipsTayside Contracts£500,000 · Closes 2 December 2026
Get tenders like this by email
New tenders like this one, in your inbox every morning. Starts with 14 days of Pro, no card needed.
Unsubscribe in one click. See our privacy policy.
Key details
Procurement
Description
The planned introduction of longer train services to the Airport in response to future demand growth will mean that double stacking arrangements of trains as currently used will no longer be viable. Through the project's Delivery Steering Group, Northern and TransPennine Express have carried out analysis which has identified that additional platform capacity is needed at the airport in order to realise the full benefit of longer train services serving the airport.
The scheme is part of a package of proposed measures in the Manchester area that are being designed/planned to boost capacity and resilience, emanating from the Cross Manchester Capacity and Reliability Improvement Study. Improving the operation of train services in the centre of Manchester and providing further capacity at Manchester Airport station, aligns with the strategic aims of Network Rail, TfGM, TfN and the wider industry. This project in in Tranche 1 of the Manchester and North West Transformation Programme (MNTP):
A remodelling of the station at Manchester Airport, specifically a platform addition or extension of multiple platforms, or provision of a new turnback facility, will be essential to accommodate the planned implementation of longer rolling stock services.
The redevelopment of these platforms will enable permissive working of two 6x24m (144m) trains, in two of the four platforms at the Airport Station. This will allow for the unaltered retention of all existing TOC services both originating and terminating at the Airport Station under 'double-stacking' conditions.
The scope areas for this package are as follows: The supply and manufacture of precast concrete SBB units & bridge cill units