B Lock Penstocks Replacement
KBS Maritime Ltd
This tender is closed to new bids.
Live now: tenders like this
- Ewenni Multi-User Bridge Replacement (and paths) - 2 Stage Design and BuildLlanharan Community CouncilCloses 20 November 2026
- Linstone Housing - RAAC Removal and Roof Replacement Works to existing propertiesLinstone Housing AssociationCloses 11 December 2026
- Door Entry Phased Replacement Programme 2026-27London Borough of HillingdonCloses 2 December 2026
- Replacement of Windows & Doors & Associated WorksCanterbury City CouncilCloses 27 November 2026
- Roof replacement and associated works at Cork College of FET St Gobans College, Seskin, Bantry, Co Cork.Cork Education and Training BoardCloses 20 November 2026
Get tenders like this by email
New tenders like this one, in your inbox every morning. Starts with 14 days of Pro, no card needed.
Unsubscribe in one click. See our privacy policy.
Key details
Procurement
- 42131220 Penstock valves
- 45221220 Culverts
- 42131120 Sluice valves
- 42131143 Flood-control valves
- 50510000 Repair and maintenance services of pumps, valves, taps and metal containers
- 42132100 Valve actuators
- 42132110 Electric valve actuators
- 42132120 Hydraulic valve actuators
- 42132130 Pneumatic valve actuators
What happened
The contract runs until 28 Feb 2030.
Description
KBS Maritime have a requirement for penstock replacements at B Lock within Portsmouth Naval Base. The project consists of 10 in number replacement penstocks in 6 chambers overall. The penstock system controls sea water via a culvert system between the harbour, the basin and the dry docks.
These include levelling penstocks of circa 8 metres deep to drainage penstocks circa 18 metres deep. The replacement programme will replace the current cast irons doors with new with specification to be agreed along with the associated shafts, wedges, door nut, brackets, platforms, ladders and actuation and road plates. This project is due to commence in Q4 2026 with all to be replaced by Feb 2030.
Contractors must be able to demonstrate design, manufacture and installation of penstock replacements in a marine environment including all site management under CDM regulations and competency of Health and Safety compliance and safe practices. Contractors must also possess at least five years' experience working within a marine environment.