Southern Water Andover Link Main (ALM) Pipeline Construction & Connection
Southern Water Services Limited
This works tender from Southern Water Services Limited closed on 6 Jun 2025. It was awarded to Clancy Docwra Limited for £39,390,096 on 2 Nov 2026. The contract end date is 8 May 2029. Region: South East. Procedure: Competitive flexible procedure.
Contracts like this usually come back out to tender before they end.
Live now: tenders like this
- TII499 Luas Finglas Main Infrastructure Design and Construction WorksTransport Infrastructure Ireland (TII)€250,000,000 · Closes 14 December 2026
- Pre Market Engagement- Construction of New Link Corridor & Associated Works. Boston Leisure Centre - Phase 2Boston Borough CouncilCloses 23 November 2026
- Tier 2 Mains Renewal Delivery & Resilience FrameworkYorkshire Water Services Limited£10,000,000 · Closes 25 January 2027
- Upper Thurne Package 3 Construction WorksBroads (2006) Internal Drainage Board£6,500,000 · Closes 19 January 2027
- Mains replacement & Associated worksCadent Gas LimitedCloses 31 August 2032
Get tenders like this by email
New tenders like this one, in your inbox every morning. Starts with 14 days of Pro, no card needed.
Unsubscribe in one click. See our privacy policy.
Key details
Procurement
Description
The Andover Link Main (ALM) scheme is being delivered by Southern Water Services (SWS) under the Major Projects Directorate. The ALM project is part of the WRMP programme and is associated with SWS’s agreement with the EA under Section 20 of the Water Resources Act 1991 put in place following Public Inquiry to reduce our abstraction licenses for public water supply. Its purpose is to provide environmental protection for the rivers Test and Itchen. The WRMP Programme aims to create greater resilience to water shortages, especially during dry weather and droughts. Existing abstraction licences for the River Test and River Itchen have been substantially reduced through changes required by the Environment Agency to protect the rivers, both designated as Sites of Special Scientific Interest (SSSI), and the River Itchen as Special Area of Conservation (SAC). Additional licence changes will bring further reductions. These rivers are key examples of rare chalk stream habitat which support a wide variety of species. The Proposed Scheme will support environmental improvement by increasing the protection of these rivers while addressing the need for secure water supply.
The ALM scheme involves approximately 25km of below-ground pipeline connecting critical infrastructure between Winchester and Andover, alongside upgrades to existing and new booster stations. It aims to deliver a bi-directional transfer capacity of 15Ml/d by March 2030, ensuring both strategic drought resilience and operational reliability for the isolated Andover Water Resource Zone (WRZ).
SWS delivery strategy is to appoint a single Principal Contractor to design and build Andover Link Main, delivery to inclue detailed design and construction package with enabling work to be completed prior to construction. This will also include support to discharge planning conditions and submission of certain environmental consent and permits. The Principal Contractor will act as a Tier 1 provider and sub-contract specialist elements. Southern Water have developed the scheme proposal to early outline design and are planning to complete this phase of work to enable the design to be realkeased with the ITT, post participation stage. comprising a detailed design and construction package, with enabling work to be completed prior to construction. This will also include support to discharge planning conditions and submission of certain environmental consent and permits.
Awarded supplier
Contact
Bid documents
Track this tender with a free account to open its bid documents.
Identifiers
Explore related tenders
External ID: fts-ocds-h6vhtk-051552 • Added 6 August 2026