DV4 Enterprise
Scottish Water
This works tender from Scottish Water closed on 6 Jan 2025. It was awarded to AECOM Limited, Stantec UK Ltd and others for £650,000,000 on 19 Mar 2026. The contract end date is 25 Mar 2033. Region: Scotland. Procedure: Negotiated procedure with prior call for competition.
Published on Scottish Water Atamis procurement portal
Contracts like this usually come back out to tender before they end.
Live now: tenders like this
- Term Extension of the National Highway's Social Enterprise Dynamic Purchasing SystemNational Highways£65,000,000 · Closes 14 August 2028
- EDC/2026/4397 Lift Refurbishment Milngavie Enterprise CentreEast Dunbartonshire CouncilCloses 23 November 2026
- Provision of a Smart Building Operations, Energy Analytics and Plant Optimisation Enterprise PlatformCork City CouncilCloses 9 December 2026
- Contractor Services Framework AgreementCaledonian Maritime Assets Ltd (Utility)£900,000,000 · Closes 22 January 2027
- Samlesbury Enterprise Zone - Foul Water DrainageLancashire County Council£2,000,000 · Closes 27 November 2026
Get tenders like this by email
New tenders like this one, in your inbox every morning. Starts with 14 days of Pro, no card needed.
Unsubscribe in one click. See our privacy policy.
Key details
Procurement
Description
Scottish Water is seeking to appoint suitably experienced Asset Delivery Partners and Primary Designer(s) and to deliver our SR27 and SR33 programme of capital works. SR27 is the regulatory period spanning from April 2027 until March 2033. SR33 is the regulatory period spanning from April 2033 until March 2039. Scottish Water aim to award this procurement by March 2026. It will run for a fixed period of seven years until March 2033 with an option to extend for a further six years until March 2039.
The Construction, Design and Management (CDM) 2015 Regulations will apply. Successful bidders will be required to utilise Scottish Waters Supply Chain and Specialist Frameworks.
To deliver the Capital Investment Programme SW is creating an Enterprise, an advanced partnering supply chain model which includes Asset Delivery Partners (ADP) and Primary Designer(s) (PD) working together in high performing integrated teams to deliver programmes of work.
The Enterprise model will have a dynamic outcome-based set of measures, with partners incentivised against service sub-programme and Enterprise outcomes and SW will have embedded resources within the Enterprise. There will also be minimum business performance thresholds in the form of KPI’s.
The Enterprise will incorporate enhanced partnering capabilities and a behavioural environment supporting closer resource integration, combined with a trading environment that also supports this approach. This will deliver affordability to support our investment targets, whilst also being adaptable and flexible enough to support changing requirements.
There will be collective focus on Beyond Zero Harm which helps us drive towards improving health, safety and wellbeing and partners will support Scottish Waters Beyond Net Zero ambitions.
This enterprise model procurement will be structured into two Lots: Lot 1 Primary Designer/s, Lot 2 Asset Delivery Partners
Full description
Scottish Water is seeking to appoint Asset Delivery Partners (ADPs) which will be accountable for driving programme/project delivery, liaising with the Enterprise Primary Designer and Integrator functions to perform Design & Build activities, while adhering to standardised designs. The ADP manages day-to-day activities during construction and coordinates the works with Scottish Water Operations until the point of asset handover.
Scottish Water is seeking to appoint suitably experienced Civils, Infrastructure and MEICA (Including Process Engineering capability) Asset Delivery Partners to deliver our SR27 and SR33 programme of capital works under an outcome-based Enterprise model. Works may include new assets and renewals, surveys and inspections, modifications, complex maintenance, refurbishments, extensions, and enhancements to existing assets. More specifically, the programmes of work based on the SR27 forecast include:
Design and construction of complex and non-complex civil engineering, mechanical, electrical, hydraulic, telemetry, control, instrumentation, and commissioning as required. This support will include works associated with new assets, renewals, modification, maintenance, and refurbishment of water and wastewater networks including mains rehabilitation and lining, sewerage networks, pumping stations and process works including mechanical, electrical, instrumentation and commissioning. The programme pipeline in SR27 includes but is not limited to UID and Flooding Network Capital Maintenance, Waste Water Treatments Works (WWTW) Upgrades & Growth, WWTW Capital Maintenance, Water Networks and new and replacement Pipelines, cleaning and maintenance, Water Treatment Works (WTW) upgrades & Capital Maintenance, Treated Water Storage build and repair.
We are looking for bidders who are committed to working in a safe, collaborative, and flexible way, who will support our drive for increased cost, carbon, time and standardisation efficiencies and who hold the appropriate capability and resources to help us deliver our strategic ambitions of Beyond Net Zero, Service Excellence and Great Value and Financial Sustainability. Successful bidders must be able to safely carry out Principal Contractor responsibilities and will be required to evidence their experience and capabilities in design and build activities for large and complex projects as well as operational requirements such as but not limited to; major water bursts, major sewer collapses and leakage support. Bidders must only bid as single entities and not as joint ventures or consortium.
The framework will be awarded from 2026-2033, with extension options, at client discretion based on business requirements, up to 2039. The estimated net value range of this procurement is £4bn - £7.7bn. Ranges are based on 2024 pricing and as such, Scottish Water reserves the right to index these values over the duration of the procurement. Successful partners will get an allocated share of this work as part of the advanced partnering approach.
Scottish Water reserves the right to augment the supply chain during SR27 to support emerging SR33 needs. SR33 is the period from 1st April 2033 until 31st March 2039. To facilitate this, a mid-point review of the SR27 supply chain will be conducted in 2030 and the current supply chain capacity and capability will be assessed at this time to ensure business requirements will be met. Based on the outcome of the review, Scottish Water reserves the right to procure additional/alternative supply chain contractor partners, as required.
The scope of the ADP (Lot 2) will be further divided into three sub-lots: 2a) Civils
- indicative works include creation of above or below ground civil structures e.g. storm tanks and treated water storage tanks.
2b) Infrastructure
- indicative works include installation of new pipework, replacement pipework, refurbished pipework or major repairs of water and sewer pipework, and water pipe lining.
2c) Mechanical, Electrical, Instrumentation, Control and Automation (MEICA) - including Process Engineering, Commissioning Engineering and Smart Technology/Internet of Things (IoT). •Mechanical: This involves the design, installation and maintenance of mechanical systems including pumps, piping and treatment processes.
- Electrical: This includes electrical site cabling, motor control centres (MCCs) and other electrical installations.
- Instrumentation: This covers the devices and systems used to measure and control variables like flow, temperature, pressure and quality
- Control: This includes operational technology, systems and software used to control and automate operational processes.
- Automation: This refers to the integration of various systems to automate processes, improving efficiency and reliability including AI and data analytics.
- Process Engineering: The includes the design, installation, integration and commissioning of process equipment to treat water and wastewater to the required standards for supply to customers or discharge to the environment.
- Commissioning Engineering: Ensures that systems and components are designed, installed, tested, operated, and maintained according to the operational requirements of the client.
- Smart Technology / IoT: Ability to design, install and commission smart technologies and IoT systems, including selecting appropriate technology, sensors, devices, and communication protocols. Ensuring these are integrated into site industrial control systems and connected to top-end communication and corporate data platforms.
These lots will be evaluated separately, and bidders are able to bid on one or multiple sub-lots. Bidders may be awarded more than one sub-lot.
Awarded suppliers (7)
Contact
Identifiers
Explore related tenders
External ID: fts-ocds-h6vhtk-04be95 • Added 6 August 2026