Communal Lighting Upgrade - IL Scheme St Marks Court
Orbit Group Limited
This works contract from Orbit Group Limited is closed to new bids. It was awarded to LOGMOOR LIMITED for £77,702 on 19 Mar 2026. The contract end date is 18 May 2026. Region: West Midlands.
Contracts like this usually come back out to tender before they end.
Live now: tenders like this
- Lighting and Road Upgrades Works, IDA Business Park, Finisklin Co. SligoIDA Ireland€350,000 · Closes 1 December 2026
- MBC-1698 SHELTERED SCHEME WORKS BRADGATE FLATS COMMUNAL AREA PROJECTWelland Procurement£125,000 · Closes 2 December 2026
- Tipperary County Council - Housing - Development of 5 No. Unit Public Housing Scheme at Micary Court, William Street, Nenagh, Co. TipperaryTipperary County CouncilCloses 18 December 2026
- Fermoy South East and South West Drainage Schemes - Pumping Stations EICA Upgrade and Operation and Maintenance ContractOffice of Public Works (OPW)€825,000 · Closes 6 January 2027
- Courts to Canopy – a Nature Restoration ProjectNeath Port Talbot County Borough Council£95,000 · Closes 27 November 2026
Get tenders like this by email
New tenders like this one, in your inbox every morning. Starts with 14 days of Pro, no card needed.
Unsubscribe in one click. See our privacy policy.
Key details
Procurement
Description
Preliminaries.
Supervision.
Principal Designer Building Control.
Building Control Application / Fee.
Welfare.
Access - Tower / Hop-Up.
Skips for Debris.
CDM Regulations.
Site Photo Survey.
DBS / ID Badges.
Lighting Survey Cost.
Cost of Luminaires.
First Floor Option B, fire rated ceiling.
Ground Floor - Cost to replace approximately 20% (46.80 m² / 13 boxes) of suspended ceiling tiles
with new matching tiles, all as agreed during tender site visit. Replace damaged / broken tiles and at
Orbit project managers instruction.
Electrical Installation - Install Lux Bright Solutions light fittings as per design / quotation document.
Provisional Sums - In connection with electrical installation as agreed during site visit:
Additional cost to provisionally wire / alter positions of light fittings, allowance 20% (34 fittings).
Install Kinetic switching if required.
1st Light Fitting.
Any looped light fitting.
F/F Fire Rated Suspended Ceiling - Provide fire hoods to 11 nr light fittings in roof void if deemed
necessary.
Builders Work - Bollards, removals & installation.
Builders Work - Making good internally to walls / ceilings.
Ongoing project management costs.
Commissioning and test costs.
Awarded supplier
Contact
Identifiers
Explore related tenders
External ID: fts-ocds-h6vhtk-068020 • Added 6 August 2026