eTenders Ireland
Reconfiguration of Renal Department, Midland Regional Hospital, Tullamore, Co. Offaly
Health Service Executive (HSE)
Awarded
IE
works
Ireland
This tender has closed
The submission deadline for this contract has passed. There may be more active works tenders from Health Service Executive (HSE), and hundreds more across the UK public sector.
Key details
Contracting authority
Region
Ireland
Contract value
€11,718,000ex VAT
Submissions closed
27 June 2024
Published
1 May 2024
Procurement
Contract period
Until 18 October 2026
8 months
Procedure type
Open Procedure
Evaluation method
MEAT
CPV classifications
- 45000000 Construction work
- 45215100 Construction work for buildings relating to health
What happened
Health Service Executive (HSE) awarded this contract to Brian Doyle and Sons Building Contractors Ltd worth €1,845,046 on 18 Feb 2026. The contract runs until 18 Oct 2026.
Description
Reconfiguration of Renal Department, Midland Regional Hospital, Tullamore, Co. Offaly
Awarded supplier
Supplier
Brian Doyle and Sons Building Contractors Ltd
Award value
€1,845,046
Award date
18 February 2026
Contact
Procurement contact for this buyer (from their other notices)
Explore related tenders
Other tenders from Health Service Executive (HSE)
View all →HSE Estates SW: Replacement of AC Multi-System - Basement CUH
HSE West Estates - McBride CNU, Westport, Co Mayo - Fire Alarm and Emergency Lighting Installation
Miscellaneous Projects at University Hospital Kerry - HSE Estates SW
CUMH Basement Fire Alarm MICC Cabling Replacement Works
2026_ EST_CN0001 - Enhanced Community Care Hub at Cavan General Hospital - Art Consultant/Project Manager€30,000
External ID: ie-3516135 • Added 18 April 2026